Processing & metallurgy

Flowsheets, pilot plants, smelting and refining

This is the work that establishes how the ore will be turned into a saleable product, and then designs and commissions the plant that does it. It starts with metallurgical test work on drill core and bulk samples — comminution testing to size mills, flotation testing to develop reagent schemes and grade-recovery curves, bottle roll and column leach tests for heap and tank leaching, settling and rheology tests for thickeners and tailings — which feeds flowsheet development and then circuit design for crushing, grinding, classification, flotation, and hydrometallurgical circuits such as heap leach, agitated leach, pressure oxidation, solvent extraction and electrowinning. Pilot plants sit between bench work and full scale, run continuously to prove recirculating loads, reagent consumption, water balance and impurity build-up that batch tests cannot see. Downstream of the mill sit smelting, refining, separation and conversion — pyrometallurgical and electrolytic steps that turn concentrate into metal or a chemical product, and which in the United States are a small, concentrated set of facilities, so the design question is often 'whose smelter, on what terms' rather than 'what plant do we build'.

18 firms working in this trade

Alphabetical. Nobody paid to be here

  • Carrier Process Equipment GroupLouisville, Kentucky

    Calcining, drying and thermal processing systems with in-house test lab

    cpeg.com
  • CoreTerTonopah, Nevada

    Toll milling — mill capacity beyond its own feed processes third-party ore for a fee; Tonopah processing site in development

    coreter.com
  • Energy FuelsLakewood, Colorado

    Uranium and vanadium milling plus rare earth processing

    energyfuels.com
  • FEECO InternationalGreen Bay, Wisconsin

    Bench and pilot testing, thermal processing and agglomeration design

    feeco.com
  • Forte DynamicsFort Collins, Colorado

    Metallurgy, process design, heap leach and recovery modeling services

    fortedynamics.com
  • Garfield RefiningPhiladelphia, Pennsylvania

    Gold, silver, platinum and palladium refining for industrial customers

    garfieldrefining.com
  • Hazen ResearchGolden, Colorado

    Metallurgical test work, flowsheet development, pilot plants and process engineering

    hazenresearch.com
  • Kappes, Cassiday & AssociatesReno, Nevada

    Metallurgical process testing, heap leach engineering and plant design

    kcareno.com
  • M3 Engineering & TechnologyTucson, Arizona

    Process and metallurgical engineering, feasibility studies and plant design

    m3eng.com
  • McClelland Laboratories, Inc.Sparks, Nevada

    Mineral processing, hydrometallurgy and environmental testing for mining clients

    mettest.com
  • MP MaterialsLas Vegas, Nevada

    Rare earth concentration, separation, refining and metal production

    mpmaterials.com
  • Nth CycleBurlington, Massachusetts

    Modular electro-extraction refining of nickel, cobalt and rare earths

    nthcycle.com
  • Phoenix TailingsExeter, New Hampshire

    Rare earth refining producing metals and alloys domestically

    phoenixtailings.com
  • ReElement TechnologiesFishers, Indiana

    Chromatographic refining of rare earth and battery elements

    reelementtech.com
  • Sabin Metal CorporationEast Hampton, New York

    Precious metal sampling, assaying and refining of industrial byproducts

    sabinmetal.com
  • Samuel EngineeringGreenwood Village, Colorado

    Process engineering, procurement and construction management for metals and minerals

    samuelengineering.com
  • The Doe Run CompanySt. Louis, Missouri

    Lead milling, smelting, refining, alloying and battery recycling

    doerun.com
  • United States Antimony CorporationDallas, Texas

    Antimony milling and smelting, including third-party raw material

    usantimony.com

Listed because we found them, not because they asked or paid. Every entry was checked against the company’s own website; none of it is an endorsement, and we have no commercial relationship with anyone on this page. Work in Processing and metallurgy and want to be added, corrected or removed? Tell us — it is free either way.

The methods, and when each is used

What each technique is for, what defines it, and where it fails

Crushing: jaw, gyratory and cone crushers

Dry, compressive size reduction from run-of-mine rock down to a size a mill or a leach heap can accept. It separates on nothing — it is a preparation step — but it sets the feed size, and therefore the energy, for every downstream operation. Jaw and gyratory do primary duty; cone crushers do secondary and tertiary duty.

Specification, and where it falls down

SpecificationFigures below are from the AMIT open-courseware mining course at the University of Alaska Fairbanks, a university teaching resource rather than a standard or a vendor specification. Jaw crusher: run-of-mine feed up to 1.5 m, product minus 300 mm for transport or minus 200 mm for SAG feed, reduction ratio 4:1 to 9:1, typically preferred for feed rates of 900 tph or less, power 2.5 to 400 kW (the course table's upper capacity figure of 13,000 tph is not credible for a jaw crusher, is inconsistent with both its own 900 tph preference and its 400 kW power ceiling, and is omitted here). Gyratory crusher: feed 1 to 1.5 m, product 10 to 15 cm, reduction ratio 3:1 to 10:1, capacity 300 to 9,100 tph, power up to 750 kW, designed for direct truck dump from trucks up to 300 tons. Standard-head cone (secondary): reduction ratio 6:1 to 8:1, closed side setting 3.2 to 38 mm, capacity 260 to 1,750 tph, power 25 to 500 kW. Short-head cone (tertiary): reduction ratio up to 10:1, closed side setting 3.2 to 19 mm. Fine-crushing cone types: feed under 50 mm, product 6 to 9 mm, reduction ratio around 8:1. US metal mining crushing energy is about 1,900 Btu per ton against 57,900 Btu per ton for grinding (US Department of Energy, Mining Industry Energy Bandwidth Study, exhibit 24).

Where it falls downCompressive crushers choke on wet, clayey or sticky feed and on tramp metal. Reduction ratio per stage is limited, so three stages are needed to reach mill feed size, and each stage needs screening and surge capacity. Product size is controlled by the closed side setting, which opens as liners wear, so product size drifts through a liner campaign. Crushers cannot make a product finer than a few millimetres economically — below roughly 5 to 20 mm, grinding takes over.

source

Tumbling-mill grinding: ball mills

Wet size reduction to the liberation size — the size at which the valuable mineral grain is detached from gangue. Nothing downstream can recover a mineral that is still locked, and nothing can recover one that has been overground to slime, so the grind target is the single most consequential number in a concentrator.

Specification, and where it falls down

SpecificationThe page cited covers ball mills and ball-mill circuits only, so no SAG, AG or rod mill figures are taken from it. Ball mills take a maximum feed around 2.5 cm; overflow-discharge mills are best suited to fine grinding to 75-106 microns while grate or diaphragm discharge mills are typically used for grinds to 150-250 microns. The ball-mill figures here come from the AMIT open-courseware mining course at the University of Alaska Fairbanks, a university teaching resource rather than a standard. Ball mill length-to-diameter ratio is normally 1.4 to 1.8; optimal speed is 70-80 percent of critical speed, where critical speed in rpm equals 42.3 divided by the square root of (mill diameter minus ball diameter); optimal ball charge is 35-45 percent of mill volume; commercial ball sizes run 10-150 mm, with steel ball bulk density 4,650 kg per cubic metre. Specific energy is estimated from the Bond equation E = Wi x (10/root P80 - 10/root F80) in kWh/t. Gold circuits commonly grind to 80 percent passing 75 microns for non-refractory ore. Grinding is about 40 percent of total US mining industry energy — roughly 494 TBtu/yr of 1,246 TBtu/yr (US Department of Energy, Mining Industry Energy Bandwidth Study).

Where it falls downTumbling mills are grossly energy-inefficient — most of the input becomes heat, noise and liner wear. Overgrinding produces slimes that are lost in flotation and gravity and that carry water into tailings. SAG mills are sensitive to feed size distribution and ore competency: a change in the coarse end of the feed can drop throughput sharply, and critical-size pebbles accumulate and must be crushed and returned. Steel media and liner wear contaminate the pulp with iron, which can consume reagents and depress flotation. Grinding is where the ore's hardness variability bites: a circuit sized on a composite work index will underperform on hard domains.

source

High-pressure grinding rolls and stirred (fine-grinding) mills

Two energy-efficient alternatives to conventional tumbling mills. HPGR crushes a compressed bed of particles between counter-rotating rolls, producing micro-cracked product that grinds more easily downstream; stirred mills use a rotating internal agitator and small media to reach fine and ultrafine sizes that a ball mill cannot economically reach.

Specification, and where it falls down

SpecificationAn industrial HPGR of 800 mm roll diameter by 400 mm width, fed minus 12 mm pre-screened material, achieved a specific energy consumption of 4.57 kWh/t at a fresh feed rate of 27.08 t/h and 107.51 t/h total throughput including circulating load, at an optimal specific pressure of 3.5-4.0 MPa (efficiency gains diminish above 4.0 MPa), producing a minus 1 mm product suitable for tower-mill feed; open-circuit P80 fell from 9.14 mm to 3.40 mm at 4.0 MPa, and a laboratory unit at 4.0 MPa used 2.02 kWh/t net. The same study reported a Bond ball work index of 16.06 kWh/t for the ore, and cited reported energy savings exceeding 45 percent for HPGR-stirred mill circuits against conventional blasting/SAG/ball mill circuits. Vertical stirred mills are restricted to a maximum feed size around 6 mm and a maximum media size around 30 mm, and a frequently quoted 1,119 kW unit rating that corresponds to one particular mill size rather than to a limit of the technology.

Where it falls downHPGR rolls wear rapidly on abrasive ore and are sensitive to tramp metal and to feed segregation; performance depends strongly on feed moisture and top size, and a circulating load of the order of 230-337 percent was reported across the tested feed range. Screening efficiency ahead of the rolls controls the circuit: in the cited work it fell from 86.45 percent at optimal conditions to 60.52 percent at maximum feed rate. Stirred mills cannot accept coarse feed at all, so they only substitute for the fine end of a circuit, and fine grinding increases slime generation and downstream water and reagent demand.

source

Classification: hydrocyclones

Splits a stream into coarse and fine fractions so that coarse material returns for more grinding and fine material advances. Screens separate strictly on size; hydrocyclones separate on settling rate, which depends on both size and density — that distinction matters, because a cyclone sends dense liberated mineral to the underflow and returns it to the mill, where it is overground.

Specification, and where it falls down

SpecificationHydrocyclone figures below are from the AMIT open-courseware mining course at the University of Alaska Fairbanks, a university teaching resource rather than a standard. Classifying cyclones are routinely applied below 300 microns. In the worked design example a 150 micron target separation size at 95 percent passing in the overflow corresponds to a corrected d50 of 110 microns, so the target separation size and the d50 are not the same number. Apex diameter is 10-35 percent of cyclone diameter and vortex finder 20-45 percent. Solids concentrations as high as 50 percent by weight are achievable without roping. Partition-curve sharpness is measured by the imperfection I = (d75 - d25) / 2 d50, with typical alpha values between 2 and 4. The page cited covers classifying cyclones only; no screening specifications are taken from it.

Where it falls downHydrocyclones bypass a fraction of the fines straight to the underflow with the water, so a cyclone is a poor classifier for fines and returns already-fine material to the mill, wasting grinding energy. Because the split is by settling rate, dense minerals report preferentially to underflow regardless of size, which is why gold and galena are chronically overground in cyclone circuits. Screens blind on near-size, wet and clay-rich material, and fine screening capacity per unit area falls steeply as aperture shrinks. Roping — a thick, unfanned underflow discharge — collapses classification completely.

source

Gravity concentration: jigs, spirals, shaking tables and centrifugal concentrators

Separates on density difference in a moving fluid. It is the oldest and cheapest concentration method and the only one that requires no chemistry, which is why it survives for gold, tin, tungsten, chromite, heavy mineral sands and coal, and is used as a scalping step ahead of flotation or leaching to catch coarse free gold.

Specification, and where it falls down

SpecificationFigures here are from the AMIT open-courseware mining course at the University of Alaska Fairbanks, a university teaching resource rather than a standard. Feasibility is judged by the concentration criterion, CC = (SG of heavy mineral minus SG of fluid) divided by (SG of light mineral minus SG of fluid): CC above 2.5 means separation is easy down to 75 microns; 1.75-2.5 is possible down to 150 microns; 1.5-1.75 down to 1.7 mm; 1.25-1.5 down to 6.35 mm; below 1.25 separation is impossible at any size. Jigs stratify a bed by pulsed fluid flow; hydraulic jigs handle coarse material and dry jigs only close-sized material. Teeter-bed (autogenous dense-medium) separators run at 1.0-2.0 tons per hour per square foot and tolerate about a 3:1 size range. Centrifugal concentrators apply roughly 60 g in fluidised-bed designs and up to 300 g in flowing-film designs, at capacities up to about 100 tph.

Where it falls downThe concentration criterion is an absolute barrier: below 1.25 no gravity device will work at any size, which rules out most sulphide-from-silicate separations. Every gravity device needs a narrow feed size range — a wide size distribution lets fine dense particles behave like coarse light ones, so classification ahead of the device is mandatory. Recovery falls away below about 75 microns for all conventional devices, and slimes must be removed or they blanket the separation. Dry jigs perform recognisably worse than hydraulic jigs because air contributes negligible density, and they tolerate only a low content of near-gravity material.

source

Dense medium separation

Sinks and floats particles in a suspension whose density is set between that of ore and waste, giving a sharp separation purely on particle density. Used as a pre-concentration step to reject barren waste at coarse size before grinding — which saves the whole downstream energy bill — and universally in coal preparation.

Specification, and where it falls down

SpecificationFigures here are from the AMIT open-courseware mining course at the University of Alaska Fairbanks, a university teaching resource rather than a standard, and describe coal preparation practice. Medium is a magnetite suspension (magnetite density 5,170 kg per cubic metre, required purity greater than 97 percent magnetics, fineness graded — a US Grade B is 95 percent passing 44 microns, with superfine around 31 microns and ultrafine around 26 microns). The underflow-to-overflow density differential is held below 0.40 relative density units. Dense medium vessels treat coarse material (plus 1/4 inch, above 6.35 mm) and are sized at 25 tons per hour per foot of overflow weir length with 260 gpm of medium per foot of weir. Dense medium cyclones treat between 3 inch and 100 mesh, are installed about 10 degrees from horizontal, operate at 9 cyclone diameters of head (10-20 psi inlet pressure) with a medium-to-solids ratio of about 5:1, and range from about 75 tons per hour at 20 inch diameter to about 416 tons per hour at 40 inch diameter. Sharpness is expressed as the probable error Ep, approximately 0.033 times separation density divided by particle size in mm. Medium is recovered by wet low-intensity magnetic drums (around 750 gauss; high-gradient rare-earth units around 21,000 gauss / 2.1 tesla), with total magnetite losses of 0.50-3.0 kg per tonne of feed.

Where it falls downSharpness collapses as particle size falls — dense medium cyclone application to 16 by 100 mesh material is limited by magnetite loss, and there is no practical dense medium route for fine material. Medium viscosity above about 20 centipoise degrades efficiency, and viscosity rises with magnetite concentration, contamination and fineness, so medium must be continuously cleaned and its contamination held below about 10 percent in both product streams. Density gradients inside the vessel trap near-density particles and cause surging, particularly with top size above 15 mm. Magnetite is a consumable and a cost, and its loss is dominated by adhesion on the drain-and-rinse screen.

source

Froth flotation

Separates on surface chemistry. Reagents make the target mineral water-repellent so it attaches to rising air bubbles and is carried into a froth, while wetted gangue stays in the pulp. It is the dominant concentration method for sulphides — copper, lead, zinc, molybdenum, nickel — and for many industrial minerals, because it is the only method that can separate minerals of similar size and density.

Specification, and where it falls down

SpecificationSeparation is principally based on differences in surface hydrophobicity, with particle size and density also significant. Reagent classes are collectors (which attach to the mineral surface and make it hydrophobic), frothers (which stabilise the bubble film), activators and depressants (which switch a mineral's floatability on or off). In copper practice the collector cited is sodium xanthate, with methylisobutyl carbinol as frother, producing a concentrate of approximately 30 percent copper; US copper recovery is quoted as 87.5 percent into concentrate (US Department of Energy, Energy and Environmental Profile of the U.S. Mining Industry: Copper). In lead-zinc practice, pH is set with lime, cyanide is used as a sphalerite depressant during galena flotation, and zinc is then activated and floated to a separate zinc concentrate. Rougher residence times, from the AMIT open-courseware mining course at the University of Alaska Fairbanks (a teaching resource rather than a standard): about 3-5 minutes for coal, 6-8 minutes for lead, 13-16 minutes for copper. Pulp density in roughing is about 4-8 percent solids for coal, 25-35 percent for lead and 32-42 percent for copper. Circuits are arranged as roughers, then scavengers, then cleaners, with roughers given maximum residence time and cleaners run for grade at lower residence time.

Where it falls downFlotation has a hard particle-size window. Below roughly 10-20 microns, bubble-particle collision probability becomes too low and fines are lost to tailings; above roughly 150-200 microns for sulphides, the bubble cannot carry the particle and it detaches — both are why the grind target is a compromise, not an optimum. It is highly sensitive to water chemistry, dissolved ions, clay slimes, oxidised mineral surfaces and iron from grinding media. Oxidised ores generally do not float without sulphidisation. Reagent suites are ore-specific and must be developed by test work; a suite that works on one domain can fail on the next. Talc, graphite and other naturally floatable gangue report to concentrate and dilute grade.

source

Magnetic and electrostatic separation

Two dry or wet physical separations on electrical and magnetic properties rather than density or surface chemistry. Magnetic separation splits on magnetic susceptibility — ferromagnetic, paramagnetic, diamagnetic. Electrostatic separation splits on the electrical conductivity of the particle surface. Together they are the backbone of heavy mineral sands processing and of iron ore concentration, and magnetic separation also recovers the medium in every dense-medium plant.

Specification, and where it falls down

SpecificationLow-intensity magnetic separators operate at flux densities of about 2,000 gauss (approximately 0.2 tesla) and recover ferromagnetic material — chiefly magnetite — and highly paramagnetic material. High-intensity separators reach up to 20,000 gauss (about 2 tesla) for paramagnetic minerals, and superconducting systems reach 60,000 gauss (6 tesla). Dry high-intensity separation is effective down to about minus 100 plus 75 micrometres; below that a wet high-intensity separator is used, and below about 500 microns dry low-intensity separation is normally replaced by wet. Ilmenite, rutile and leucoxene behave as conductors; zircon, sillimanite, garnet, monazite and quartz behave as non-conductors.

Where it falls downMagnetic separation only works where there is a susceptibility contrast — it is useless on a suite of similarly paramagnetic silicates, and the cited review notes that magnetic concentration may not be satisfactorily efficient for particles finer than about 100 micrometres, because magnetic force on a particle falls faster than the competing drag and gravity forces. Middlings containing intergrown magnetic and non-magnetic phases report to whichever product the field strength favours, so liberation governs the result. Electrostatic separation requires a dry feed, because residual surface moisture short-circuits the surface charge, so feed is normally dried and heated; the optimum temperature is feed-specific and is established by test work rather than fixed by any general threshold. It is also restricted to a narrow size band and to single-layer feed presentation, which caps throughput per unit.

source

Leaching: heap, dump, vat, tank/agitation, in-situ, pressure and biological oxidation

Separates on solubility — a chemical reagent dissolves the target metal and leaves the gangue behind, so liberation by grinding is partly or wholly avoided. Heap and dump leaching handle low-grade ore at very low cost; tank leaching handles higher-grade material fast; in-situ recovery dissolves the metal without moving the rock; pressure and biological oxidation are pretreatments that destroy the sulphide matrix locking gold in refractory ore.

Specification, and where it falls down

SpecificationPublished heap-leach ranges across commodities (2019 review in Sustainability): gold recovery 30-95 percent, with reported cycle times of 40 to 60 days; copper recovery reported across individual cases from about 53 to 77 percent, with sulphuric acid consumption of 25-75 kg per tonne of ore, one case reaching 73 percent in 140 days at 25 degrees C; uranium about 70 percent in one to six months; agglomeration of crushed ore with lime, Portland cement or fly ash before stacking to preserve permeability. Design practice for gold tank leaching (SAIMM, 1999) uses 6 to 12 leach reactors in series, 20-40 hours total residence, about 50 percent solids, 200-250 ppm cyanide in the first vessel falling to a minimum around 120 ppm in the last, at a grind of typically 80 percent passing 75 microns. In-situ recovery of uranium injects a lixiviant of water with oxygen or hydrogen peroxide plus sodium carbonate or carbon dioxide, recovers it through production wells and strips the uranium by ion exchange to yellowcake. Pressure oxidation of a pyrite-arsenopyrite concentrate (Processes, 2023, the source cited in this category's numbers list): 200 degrees C, 7 bar oxygen, 1 hour (typical POX residence for such concentrates is 30-60 minutes), giving 97-99 percent sulphide sulphur oxidation and 96-97 percent subsequent gold recovery. Stirred-tank bio-oxidation: 40 degrees C, 15 percent pulp density, three reactors in series at 2 days each, giving 43 percent sulphide oxidation and 68 percent gold recovery at 2 days, 74 percent and 82 percent at 4 days, and 79 percent and 88 percent at 6 days.

Where it falls downHeap leaching trades recovery for cost: reported gold heap-leach recoveries run as low as 30 percent, so a large fraction of the contained gold and silver may never be extracted. Permeability governs everything — clay, fines migration, over-compaction and poor agglomeration create channelling and dead zones no amount of extra cycle time will fix. Acid-consuming gangue (carbonates, some silicates) can make copper heap leaching uneconomic regardless of copper grade. Cyanide leaching fails on refractory ore where gold is locked in sulphide or associated with carbonaceous material, which is what forces the POX or bio-oxidation route. Bio-oxidation is slow, temperature- and pH-sensitive, and poisoned by chloride and some metals; pressure oxidation needs expensive acid-resistant pressure vessels and produces an acidic residue requiring neutralisation. In-situ recovery is restricted to permeable, confined, saturated host rock and carries an aquifer-restoration obligation.

source

Recovery from solution: carbon-in-pulp, carbon-in-leach, solvent extraction and electrowinning

Takes dissolved metal out of a dilute leach solution and concentrates it into a saleable product. Activated carbon adsorbs gold cyanide complexes directly from pulp (CIP) or from pulp while leaching continues (CIL). Solvent extraction uses an organic reagent to selectively transfer copper from a dilute, impure leach solution into a clean, concentrated electrolyte. Electrowinning then plates the metal out with direct current.

Specification, and where it falls down

SpecificationCIP design practice: carbon at 10-25 grams per litre of pulp (0.5 to 1.2 percent by volume), typically 6 to 8 adsorption tanks with a mean pulp residence time of about an hour per tank, interstage screens of 0.6-0.8 mm aperture, loaded carbon values on operating plants ranging from 300 to 20,000 grams of gold per tonne of carbon, gold recovery from solution of 90-99 percent depending on feed tenor, and adsorption tails solution of 0.01 to 0.005 grams per cubic metre regarded as practically achievable. Elution at 90-120 degrees C in 0.1 to 2 percent by mass sodium cyanide and 0.1 to 2 percent sodium hydroxide, targeting eluted carbon below 40 grams per tonne, followed by regeneration in a rotary kiln at 650-750 degrees C in a steam atmosphere to limit oxidation. Copper electrowinning (SAIMM Journal volume 109 number 6 page 343, 2009, not the carbon-in-pulp paper cited for this entry): current densities vary between 200 and about 375 A per square metre, with 250-300 A per square metre typical after solvent extraction; about 2 to 2.3 V per cell; current efficiency as high as 95 percent after solvent extraction but as low as 65 percent for direct electrowinning; electrolyte copper tenor 25-50 g/L; 1.54 g of sulphuric acid is regenerated for every gram of copper plated, from the stoichiometry CuSO4 + H2O giving Cu + H2SO4 + half O2, which is 98.08 g of acid per 63.55 g of copper (the cited electrowinning paper prints 1.98 g per gram, which does not follow from that reaction); optimum electrolyte temperature 45-55 degrees C for conductivity but held below 40 degrees C where solvent extraction is upstream; a cathode deposition cycle longer than eight days is not recommended. US Department of Energy figures (Energy and Environmental Profile of the U.S. Mining Industry: Copper) put hydrometallurgical copper processing at 1,490 Btu per ton against 484,000 Btu per ton for pyrometallurgical processing.

Where it falls downCarbon adsorption is defeated by preg-robbing carbonaceous ore, where natural organic carbon in the ore adsorbs the gold before the activated carbon can — CIL exists precisely to compete with it, and where it fails a blanking or oxidation step is needed. Carbon attritions and is lost, carrying gold with it, and fouls with organics, calcium carbonate and silica, which is why acid washing and thermal regeneration are mandatory. Solvent extraction requires a solution clean enough and of sufficient copper tenor to be worth treating, is sensitive to entrainment losses of organic, to crud formation at the interface, and to manganese and chloride in the leach solution. Electrowinning current efficiency falls sharply with iron in the electrolyte, which cycles between oxidation states and consumes current; short circuits between electrodes waste current and damage cathode quality; and lead anodes contaminate cathode with lead unless controlled.

source

Roasting, smelting, converting and electrorefining

Pyrometallurgy separates on chemical affinity and on the immiscibility of molten phases. Roasting removes sulphur and volatiles from a concentrate as a gas and converts sulphides to oxides. Smelting melts the charge so that copper-bearing sulphide (matte) separates by density from a silicate slag. Converting blows air through the matte to remove iron and then sulphur, giving blister copper. Fire refining and electrorefining then take blister to commercial-purity cathode.

Specification, and where it falls down

SpecificationCopper (EPA AP-42 Section 12.3, a 1990s document): concentrate fed to the smelter grades 15 to 35 percent copper; roasting is carried out at about 650 degrees C (1,200 degrees F) and removes 20-50 percent of the sulphur as sulphur dioxide; reverberatory smelting temperature may exceed 1,500 degrees C (2,730 degrees F) — reverberatory furnaces are documented in AP-42 but are historical, not current US primary practice — while flash furnaces run at approximately 1,000 degrees C (1,830 degrees F); matte ranges from 35 to 65 percent copper with 45 percent the most common; converting yields blister copper at 98.5 to 99.5 percent copper; the anode furnace is maintained at 1,100 degrees C (2,010 degrees F); electrorefined cathode is 99.95 to 99.96 percent pure. Off-gas sulphur dioxide strengths: fluidised-bed roasters 10-12 percent, flash furnaces 10-70 percent, converters 4-7 percent. Conventional copper smelting is quoted at 30.92 to nearly 40 million Btu per ton of cathode copper recovered, with conventional smelting recovery of 98.7 percent (US Department of Energy, Energy and Environmental Profile of the U.S. Mining Industry: Copper; neither figure is in AP-42). Zinc roasting and electrolytic zinc figures have been removed from this entry: AP-42 Section 12.3 covers primary copper smelting only.

Where it falls downSmelters are capital-intensive, scale-dependent and inflexible — they need a steady concentrate supply of predictable chemistry. Penalty elements in concentrate (arsenic, antimony, bismuth, fluorine, mercury, chlorine) are charged against the seller and can make a concentrate unsaleable regardless of copper grade. Sulphur dioxide must be captured and converted to acid, which ties the smelter to an acid market; converter gas at 4-7 percent SO2 is the weakest and most difficult stream. Electrorefining is slow, works only on an anode already close to specification, and generates an anode slime that must itself be processed to recover gold, silver, selenium and tellurium. Roasting a gold concentrate mobilises arsenic and mercury and requires dedicated gas cleaning.

source

Tailings dewatering: thickening and filtration

Removes water from the tailings stream so it can be returned to the plant and so the tailings can be deposited as a thickened, paste or filtered (dry-stack) material rather than a pumped slurry. It separates nothing of value — it separates water — but it determines the water balance, the deposition method and the failure mode of the storage facility.

Specification, and where it falls down

SpecificationConventional slurry tailings are typically about 20 to 40 percent solids by weight and up to 60 percent. High-density thickened and paste tailings are typically 60 to 75 percent solids by weight; high-rate and high-capacity thickeners produce conventional thickened underflow at 50-65 percent solids, high-compression thickeners produce underflow at high yield stress and high solids, and deep-cone paste thickeners reach up to 70 percent solids. High-density thickened and paste tailings have shear yield stresses from 40 Pa to 200 Pa and therefore require positive-displacement pumps. Filtered tailings are typically dewatered to more than 80 percent solids and often close to optimum moisture content, and give the highest water recovery during processing. In concentrate handling the same sequence is used: concentrate is thickened by settling, pumped out, dewatered by a filter press and dried.

Where it falls downDewatering rate is governed by particle size and clay content — a fine, clay-rich or high-slimes tailing settles slowly and holds water regardless of equipment, which is the practical ceiling on thickener underflow density. Flocculant is a continuing chemical cost and its dose must be retuned as ore changes. Paste and filtered tailings demand far more energy and capital than slurry, and filtered stacks require external water management because they hold little water on the facility. Thickener upsets — bed level loss, rat-holing, rake torque — propagate straight back into the plant water balance.

source

The protocols that decide whether a result is trustworthy

The procedures between a sample and a number you can rely on

Metallurgical test work sequence

The staged programme that takes an ore from first sample to plant design, escalating in sample mass, cost and confidence at each study level. The sequence exists because each stage is designed to kill a flowsheet cheaply before the next stage spends more on it.

What the procedure actually requires

Published study-stage framework: scoping study at an order of accuracy of plus or minus 30-35 percent with a block-diagram flowsheet and essentially no test work; preliminary/prefeasibility study at plus or minus 20-25 percent with an outline flowsheet and small-scale testing of milling, flotation and refractory gold treatment; detailed/feasibility study at plus or minus 10-15 percent with SAG/AG tests, locked-cycle flotation and pilot plant programmes; then design with final specifications and detailed test work across all unit operations. Head grade analysis is not confined to the valuable elements but includes elements that constrain throughput and recovery, such as sulphur and arsenic. Sample types are variability samples (individual drillhole intersections or composites representing metallurgically distinct ore types), composite samples for testing reagent and flowsheet variables, and bulk samples for piloting, requiring 20 to 100 tonnes for a large-scale pilot run.

source

Comminution test work and sample requirements

The battery of standard grindability and breakage tests used to size crushers and mills. Each test has a defined feed preparation, closing screen and sample mass, and the mass requirement is the practical constraint on how early in a project comminution can be characterised from drill core.

What the procedure actually requires

Published feed size and sample mass requirements: Bond crushing work index on minus 90 plus 60 mm or minus 40 plus 20 mm feed requiring 10 kg; Bond rod mill work index on minus 12.7 mm feed requiring 25 kg; Bond ball mill work index on minus 3.35 mm feed requiring 25 kg; drop-weight breakage parameter tests on minus 100 mm feed requiring 100 kg; advanced media competency testing on minus 200 mm feed requiring about 1,000 kg, or about 150 kg using PQ drill core; pilot plant comminution on 200 mm feed requiring about 10 to 15 tonnes per trial.

source

The Bond work index and grinding specific energy

The standard empirical index for the energy required to grind an ore, expressed in kWh per tonne. It is the number a mill is sized on, and it is defined relative to a specific transfer size, so a work index quoted without its P80 and F80 is meaningless.

What the procedure actually requires

The Bond equation as taught for ball mill circuits: E = Wi x (10 divided by the square root of P80, minus 10 divided by the square root of F80), in kWh per tonne, where P80 and F80 are the 80 percent passing sizes of product and feed in micrometres and Wi is the work index; Wi must be adjusted for non-standard operating conditions. A published industrial-scale HPGR study (Minerals, 2025) gives a Bond ball work index of 16.06 kWh/t for the ore tested, against which an HPGR stage achieved 4.57 kWh/t of specific energy at 27.08 t/h fresh feed. Bond power draw for a ball mill is estimated from a separate published equation in kW as a function of ball charge fraction, fraction of critical speed, ball bulk density, mill length and mill diameter to the power 2.3.

source

Bench flotation, locked-cycle testing and variability testing

The three-level flotation test sequence. Batch rougher and cleaner tests scan variables cheaply; locked-cycle tests recirculate the middlings streams until the circuit reaches equilibrium, which is the only bench test that predicts a real continuous circuit's grade and recovery; variability tests apply the chosen conditions to many individual samples to show how the answer moves across the orebody.

What the procedure actually requires

Published practice: begin with batch laboratory rougher and cleaner flotation tests to evaluate the major variables including grind size, reagent types and flowsheet alternatives; follow with locked-cycle test work once a preliminary flowsheet exists, testing sufficient cycles to ensure that equilibrium is reached; assess variability using either bench-scale batch test work or locked-cycle test work depending on circuit complexity and separation efficiency. Pilot flotation test work is run to generate sufficient concentrate and tailings samples for downstream test work such as roasting and thickening, and to allow operator training before plant operation.

source

Mass balance, the two-product formula and metallurgical accounting

The arithmetic that converts three assays into a mass split, a recovery and a concentration ratio, and the reconciliation that follows when the numbers do not close. Every recovery figure quoted for a plant or a test is the output of this calculation.

What the procedure actually requires

The governing rule is that mass can neither be created nor destroyed: mass in equals mass out. For a single separation, Ff = Cc + Rr, where F, C and R are the mass flows of feed, concentrate and tailings and f, c and r are their assays. The two-product formula gives mass yield from assays alone: Y = C/F = (f - r) / (c - r). Component recovery is (c/f) x Y. The ratio of concentration is F/C, tonnes of feed per tonne of concentrate, which is the reciprocal of the mass yield; c/f is the enrichment or upgrade ratio. The cited course page calls c/f the concentration ratio, which is against standard usage. Worked example: feed 0.50 percent Cu, concentrate 24.5 percent Cu, tailings 0.14 percent Cu gives a mass yield of 1.48 percent, a copper recovery of 72.4 percent and a ratio of concentration of about 68 tonnes of feed per tonne of concentrate (the cited course page reports 73.5 percent recovery by feeding its rounded 1.5 percent yield back into the recovery formula). The formula is very sensitive to variation in the tailings assay r and gives inaccurate results where separation is incomplete. When several assayed components give different calculated yields from the same mass-flow data, the dataset contains measurement error and must be adjusted by weighted least squares — that adjustment is data reconciliation.

source

Grade-recovery relationship

The trade-off curve every concentrator operates on: recovery can almost always be raised by accepting a lower concentrate grade, and grade raised by accepting lower recovery. A single grade-recovery point means nothing without the curve it sits on, and comparing two flowsheets at different grades is meaningless.

What the procedure actually requires

Reported plant data illustrating a single operating point on such a curve: copper recovery 77.9 percent at a concentrate grade of 26.3 percent Cu, and gold recovery 71.2 percent at a concentrate grade of 81.0 g/t, from the Cadia plant metallurgical balance reproduced in the AMIT open-courseware mining course at the University of Alaska Fairbanks, a teaching resource rather than a standard. US copper industry figures (US Department of Energy, Energy and Environmental Profile of the U.S. Mining Industry: Copper) are given as 87.5 percent recovery into concentrates at a concentrate grade of approximately 30 percent copper, and 98.7 percent recovery in conventional smelting. Concentration ratio (concentrate grade divided by feed grade) and separation efficiency are the standard derived measures; a rougher is operated at maximum residence time for recovery while cleaners are operated at lower residence time for grade.

source

Sampling of a moving stream

The rules that make a sample representative of the stream it came from. A sampling error made here cannot be recovered by any amount of analytical precision downstream, and it propagates into every recovery, reconciliation and payment calculation.

What the procedure actually requires

Correct practice for a cross-stream cutter (2014 SAIMM overview of sampling best practice in African mining; the rules are ISO-derived and not region-specific): the collector opening should be at least three times the nominal top size of the particles, and not less than 10 mm for fine dry solids or 50 mm for wet solids; the collector should start outside the stream and reach constant speed before entering it; collector speed should not exceed 0.6 m/s; and material must be collected from the complete cross-section of the stream, so the cutter takes a full slice rather than a part of the flow. For slurry sampling, sampling frequency should be not less than once every five minutes. The fundamental sampling error variance is the absolute minimum sampling error for a given fragment size and sample mass, can be calculated before the sample is taken, and is reduced by decreasing the nominal fragment size or increasing the sample mass — which is what determines the correct sample mass.

source

Specifications worth knowing

Technical figures, each linked to the document it came from

  • Metal mining: grinding 57,900 Btu per ton, blasting 9,900 Btu per ton, crushing 1,900 Btu per ton, flotation separation 900 Btu per ton; grinding is about 494 TBtu/yr of 1,246 TBtu/yr total US mining energyDOE benchmark of where energy actually goes in a US mining operation — grinding dominates everything else by more than an order of magnitude.source
  • Bond ball mill work index 16.06 kWh/t for the ore studied; HPGR specific energy 4.57 kWh/t at 27.08 t/h fresh feed and 3.5-4.0 MPa; P80 reduced from 9.14 mm to 3.40 mm in open circuitMeasured industrial-scale comminution energy for an HPGR stage against the Bond index of the same ore.source
  • Ball mill overflow discharge best suited to grinds of 75-106 microns; grate/diaphragm discharge typically to 150-250 microns; optimum 70-80 percent of critical speed; 35-45 percent ball chargeThe practical grind-size windows and operating settings for the two standard ball mill discharge arrangements.source
  • Gold circuits: grind typically 80 percent passing 75 microns; 20-40 hours leach residence in 6-12 reactors at about 50 percent solids; 200-250 ppm cyanide falling to about 120 ppm; carbon at 10-25 g/L of pulp; loaded carbon 300-20,000 g Au/t; 90-99 percent gold recovery from solutionDesign figures for a conventional leach and carbon-in-pulp gold circuit.source
  • Copper: concentrate fed to smelter 15-35 percent Cu; matte 35-65 percent Cu (45 percent most common); blister 98.5-99.5 percent Cu; electrorefined cathode 99.95-99.96 percent; roasting about 650 degrees C, reverberatory smelting above 1,500 degrees C, anode furnace 1,100 degrees CThe full grade and temperature ladder from copper concentrate to refined cathode.source
  • Copper electrowinning: 200 to about 375 A per square metre (250-300 typical after solvent extraction), 2-2.3 V per cell, current efficiency up to 95 percent after SX but as low as 65 percent for direct electrowinning, electrolyte 25-50 g/L Cu, cathode cycle not more than eight daysOperating envelope for a copper electrowinning tankhouse.source
  • Pressure oxidation at 200 degrees C and 7 bar oxygen for 1 hour gave 97-99 percent sulphide sulphur oxidation and 96-97 percent gold recovery; stirred-tank bio-oxidation at 40 degrees C and 15 percent pulp density gave 79 percent sulphide oxidation and 88 percent gold recovery after 6 daysMeasured performance of the two competing oxidative pretreatments for refractory gold concentrate.source
  • Conventional slurry tailings about 20-40 percent solids (up to 60); thickened and paste tailings 60-75 percent solids with shear yield stress 40-200 Pa; filtered/dry-stack tailings more than 80 percent solidsThe solids-content bands that define each tailings deposition technology and the pumping regime each requires.source

How it is actually bought

Contract shapes and what they price

Test work is bought as a written programme against a published schedule of rates — a price per sample, per test, per assay suite — placed with an accredited laboratory, with the sample chain of custody, the residue retention period and the ownership of raw data written into the order rather than assumed. Flowsheet development and plant design are bought in the same stage-gate way as mine engineering, then delivered either as an EPC lump-sum turnkey package, where the contractor carries schedule and process performance risk and prices it accordingly, or as EPCM on a reimbursable-plus-fee basis, where the owner keeps the risk and the visibility. The commercial teeth in a process contract are the process guarantees: a defined feed specification, a named throughput and recovery at that feed, an agreed performance test protocol and duration, liquidated damages or retention held against passing it, and a clear statement of what happens if the ore does not match the design basis. Pilot plant campaigns are usually cost-plus with a fixed facility day rate and a separately priced sample preparation and assay bill. Smelting, refining and toll conversion are bought as offtake or tolling contracts priced on treatment and refining charges with payable metal percentages, deleterious element penalties and price participation, not as engineering fees at all.

Who regulates it

And what each one requires of this trade

  • EPA / delegated state air agency — NESHAP for primary copper smelting (40 CFR 63 Subpart QQQ) — Applies to primary copper smelters that are major HAP sources — 10 tons per year of any single HAP or 25 tons per year of any combination — and sets filterable particulate limits on concentrate dryers, smelting and slag cleaning vessels, mercury limits, and work practice standards including fugitive capture during matte and slag tapping and a fugitive dust control plan.
  • EPA — RCRA and the Bevill exclusion — Extraction and beneficiation wastes plus exactly 20 named mineral processing wastes — including primary copper and lead slag, bauxite refining red and brown muds and phosphogypsum — are excluded from federal hazardous waste regulation under Subtitle C; every other mineral processing waste stream is regulated, including under land disposal restrictions, so where a flowsheet puts the boundary between beneficiation and processing changes the waste liability.
  • EPA / NPDES permitting authority — Ore Mining and Dressing effluent guidelines (40 CFR 440) — Sets technology-based effluent limits for 13 ore subcategories from iron and aluminium through the copper-lead-zinc-gold-silver-molybdenum group to gold placer mines, which become enforceable numbers in the site's discharge permit and therefore constrain water balance and treatment design.
  • Mine Safety and Health Administration (MSHA) — A mill, leach pad or refinery on mine property is regulated by MSHA, not OSHA, under 30 CFR Part 56 for surface and Part 57 for underground metal and nonmetal operations, covering ground control, fire prevention, air quality, electricity, machinery and equipment, materials storage and handling and personnel hoisting.
  • Nuclear Regulatory Commission or Agreement State — 10 CFR Part 40 — Licenses domestic possession, use, transfer and disposal of source and byproduct material, which brings uranium milling, heap leach and in-situ recovery operations and their tailings under a specific source material licence with its own Appendix A criteria.

The standards that apply

Ask which of these a firm works to

  • 40 CFR Part 440 — Ore Mining and Dressing Point Source Category — For copper, lead, zinc, gold, silver and molybdenum mills using froth flotation, best practicable technology limits include total suspended solids at 30 mg/L daily maximum and 20 mg/L on a 30-day average, copper at 0.30 and 0.15 mg/L, zinc at 1.0 and 0.5 mg/L, lead at 0.6 and 0.3 mg/L, mercury at 0.002 and 0.001 mg/L, cadmium at 0.10 and 0.05 mg/L, and pH within 6.0 to 9.0.
  • 40 CFR Part 63 Subpart QQQ — NESHAP, primary copper smelting — Sets filterable particulate matter limits of 50 mg/dscm for existing and 23 mg/dscm for new concentrate dryers and 6.2 mg/dscm for smelting vessel process off-gas, plus mercury limits of 0.033 lb/hr existing and 0.00097 lb/hr new, with further limits for benzene, toluene, chlorine, hydrogen chloride, PAH, naphthalene and dioxins/furans.
  • ISO/IEC 17025:2017 — competence of testing and calibration laboratories — Specifies general requirements for the competence, impartiality and consistent operation of laboratories, and is the standard a buyer should require of any laboratory producing the assays and metallurgical results that a reserve statement or a plant design will rest on.
  • International Cyanide Management Code (the Cyanide Code) — A voluntary code for gold and silver mining, cyanide production and cyanide transport under which a designated operation must complete the on-site portion of its initial certification audit within three years of designation, notify the Institute at least 60 days before the audit, have the lead auditor submit findings within 90 days, and re-audit on a three-year cycle using auditors meeting the Institute's independence and experience requirements.
  • OSHA 29 CFR 1910.119 — Process Safety Management — For refineries, smelters, acid plants and reagent systems that sit off mine property, PSM is triggered by an Appendix A chemical at or above its threshold quantity or by 10,000 pounds or more of a Category 1 flammable gas or a flammable liquid with a flashpoint below 100 degrees Fahrenheit, and then requires 14 elements including process hazard analysis, mechanical integrity, management of change, pre-startup safety review, contractor management and three-yearly compliance audits.

What to demand from a firm

Credentials worth checking before you sign

Where to find firms yourself

Public registers and member directories

  • ANAB accredited laboratory search — The ANSI National Accreditation Board accredits testing laboratories to ISO/IEC 17025:2017 and publishes a searchable directory of accredited laboratories, reachable from its ISO/IEC 17025 programme page, so a buyer can confirm an assay or metallurgical laboratory's accreditation and scope independently of the lab's own marketing.
  • A2LA Directory of Accredited Organizations — A free public search of accredited organisations by keyword (scope, test method, certificate number, organisation name), accreditation programme (ISO/IEC 17025, 17020, 17043, 17065, 17034, 20387, 17029 and others), country and region, with separate searches for suspended or withdrawn certificates and for false accreditation claims.
  • Cyanide Code Signatory Directory — A public directory of signatory mining operations, cyanide production facilities and transporters with their current certification status and a map of countries of operation — roughly 70 mining operations, 50-plus production facilities and 150-plus transport providers.
  • SME Registered Member Directory — A searchable roster of Registered Members of the Society for Mining, Metallurgy & Exploration by specialised function, which is the practical way to find named metallurgists and process engineers rather than firms.

Numbers worth knowing

Each one carries its source

40% of US mining industry energy use is grinding

The Department of Energy's US Mining Industry Energy Bandwidth Study found grinding consumed roughly 494 trillion BTU per year of a 1,246 trillion BTU per year industry total, with materials handling next at 17%, and beneficiation and processing together about 44% (some 546 TBtu/yr). This is why comminution circuit selection dominates operating cost, and it is the number that should govern how much a buyer spends on comminution test work.

source
2 primary smelters and 2 primary electrolytic refineries

The entire US primary copper smelting and electrolytic refining capacity in 2025, alongside 2 secondary smelters, 14 electrowon refineries and 4 secondary refineries, serving 1.0 million tons of recoverable mine production from 26 mines (17 of which made over 99% of output); net import reliance was 57% of apparent consumption, up from 45% in 2024.

source
160 tons of gold from more than 40 lode mines; top 25 operations produced 94%

US gold mine production in 2025, drawn from more than 40 lode mines in 12 states plus placer operations, with Nevada at about 64% and Alaska about 22% of output, and commercial-grade gold produced at approximately 16 refineries.

source
10 tons per year of one HAP, 25 tons per year combined

The major source threshold that pulls a primary copper smelter into the Subpart QQQ NESHAP, with existing-source mercury limited to 0.033 lb/hr and new sources to 0.00097 lb/hr.

source
20 mineral processing wastes

The number of mineral processing waste streams excluded from federal hazardous waste regulation under the Bevill exclusion; all other mineral processing wastes remain regulated under RCRA, including land disposal restrictions.

source

How this goes wrong

The specific traps, not general advice

  • Sizing a plant from bench-scale batch results with no continuous pilot campaign. Recirculating loads, reagent build-up, impurity accumulation, water balance and settling behaviour only appear when the circuit runs closed, and they are exactly what destroys throughput and recovery in the first year.
  • Paying for assays from a laboratory whose accreditation does not cover the method used. Accreditation is granted scope by scope; a general claim of ISO/IEC 17025 status is not the same as accreditation for the specific fire assay, leach or multi-element method your reserve statement will rest on.
  • Signing a process guarantee with no feed specification. A recovery guarantee without a defined head grade, mineralogy, hardness and deleterious element range is unenforceable, and the argument that follows is always 'the ore changed'.
  • Ignoring where the flowsheet draws the line between beneficiation and mineral processing. Only 20 named mineral processing wastes are Bevill-excluded; a circuit change that converts a beneficiation residue into a regulated processing waste can add a hazardous waste liability that dwarfs the capital saving.
  • Designing a concentrate without asking who will smelt it. With only two primary copper smelters and two primary electrolytic refineries in the country, a concentrate with a penalty element problem can be technically excellent and commercially unplaceable.

The vocabulary

Defined by someone who is not selling you anything

P80
The screen size through which 80 percent of a stream passes — the standard single-number description of a size distribution. F80 is the same measure for a feed, P80 for a product; a grind target is normally quoted as an 80 percent passing size in micrometres.
Work index
An ore's resistance to grinding, in kilowatt-hours per tonne, defined relative to specified feed and product 80 percent passing sizes. It is the number a mill is sized on, and separate indices exist for crushing, rod milling and ball milling.
Circulating load
The material returned from a classifier to the mill, expressed as a percentage of new feed. A grinding mill in closed circuit may be processing several times its fresh feed tonnage; the circulating load is what allows the mill to make a controlled product size rather than an uncontrolled one.
Liberation
The degree to which valuable mineral grains have been detached from gangue by grinding. A particle that is still intergrown is 'locked' and will report to the wrong product in any physical separation — liberation size is what sets the grind target.
Recovery
The percentage of the metal or mineral in the feed that reports to the saleable product. It is calculated from assays and mass flows, not measured directly, and is always quoted against a specific concentrate grade.
Concentrate grade
The assay of the product stream — percent copper, percent zinc, grams per tonne gold. Concentrate grade and recovery trade against each other, so one is never meaningful without the other.
Tailings
The rejected stream from a concentration process: ground rock plus process water plus residual reagents. It is the largest mass flow in any concentrator and its water content determines how it is stored.
Reagent suite
The specific set of chemicals, dosages and addition points used to make a flotation circuit work on a particular ore. It is ore-specific, developed by test work, and must be re-tuned as ore types change.
Collector
A flotation reagent that adsorbs on the target mineral's surface and makes it water-repellent so that it attaches to air bubbles. Xanthates are the classic sulphide collectors; hydrocarbon oils are used for naturally floatable minerals.
Frother
A surface-active reagent that stabilises the air bubbles and the froth layer so that loaded bubbles survive to be scraped off. Alcohols such as methylisobutyl carbinol are common frothers; frother controls bubble size and froth persistence, not mineral selectivity.
Depressant
A reagent that prevents a mineral from floating, so that another can be floated selectively. Lime depresses pyrite by raising pH; cyanide depresses sphalerite while galena is floated; sodium silicate disperses and depresses silicate gangue.
Pregnant solution
A leach solution carrying dissolved metal, on its way to a recovery step such as carbon adsorption, solvent extraction or precipitation. Also called pregnant leach solution.
Barren solution
The solution left after the metal has been stripped out, which is reagent-adjusted and recycled back to the leach. Barren solution tenor is the direct measure of how well the recovery step is working.
Raffinate
The aqueous stream leaving a solvent extraction circuit after the metal has been transferred to the organic phase. In a copper heap-leach operation the raffinate is acidified and returned to the heap.
Dore
An impure gold-silver alloy bar, produced by melting the precipitate or the electrowinning product at a mine site. It is the mine's saleable product for precious metals and is sent to a refinery for final separation.
Matte
The molten copper-iron-sulphide phase produced in smelting, which separates from the silicate slag by density. It typically ranges from 35 to 65 percent copper, with about 45 percent most common, and is the feed to converting.
Blister copper
The product of converting, at roughly 98.5 to 99.5 percent copper. It is named for the gas blisters formed on its surface as dissolved sulphur dioxide escapes during solidification, and it still requires fire refining and electrorefining.
Refractory ore
Ore from which the target metal cannot be recovered by conventional means — for gold, ore where the gold is locked inside sulphide minerals or associated with carbonaceous material, so that cyanide cannot reach it without an oxidative pretreatment such as roasting, pressure oxidation or bio-oxidation.
Preg-robbing
The behaviour of naturally carbonaceous ore, in which organic carbon in the ore adsorbs dissolved gold out of the leach solution before it can be recovered. Carbon-in-leach exists partly to compete with this effect by putting activated carbon in the tank alongside the ore.
Payable metal
The portion of metal in a concentrate that the buyer actually pays for, after deducting a fixed unit deduction and applying a payable percentage, and after penalties for deleterious elements. It is always less than the assayed metal content.

Questions to ask before you sign

  • Have you run this ore type, or something genuinely comparable?
  • What recovery does the test work support, at what grind and what cost?
  • Is the capacity you are describing built, permitted, or proposed?

Where to next

Every figure and requirement on this page is linked to the agency, standard or register it came from. Nothing here is legal advice, rules change, and a link is worth more than our summary of it — follow them.